PROJECT DESCRIPTION

blubar.gif (1127 bytes)

BULLET PRESENT STATUS:

   
blubul.gif (897 bytes) Detailed Engineering Design for Phase I, IA and IB:

Detailed Engineering Design for 375Km in Phase I was completed on March,1999 and for another 375 Km in Phase IA on June 30,1999 and for 12 byepasses was completed under Phase IB in March 2001 by M/s. Kinhill Pty Ltd., Australia.

blubul.gif (897 bytes) Prequalification of Contractors for Contract TNRSP 01, 02, 03 & 04

After prequalification, the bids were received on October 14 & 15, 2003.  Bid evaluation has been completed for package 01. No objection of the World Bank on bid evaluationand award of contract has been obtained. Letter of Acceptance has been issued on 09.09.2004. Bid evaluation of package 02, 03 & 04 duly approved by steering committee sent to World Bank.

 

blubul.gif (897 bytes) Construction Supervision for Contract TNRSP 01, 02, 03 & 04

It is proposed to appoint Consultants to supervise the works in different contracts.  The agreement has been signed on March 31, 2004 with M/s Lea International Ltd, Canada for package 01 (SC-1) and the value of consultancy services is Rs.19.07 crores and the consultant is reviewing the design and engineering reports. The agreement has been concluded on 10.09.2004 with successful consultant M/s Sheladia Associates Inc, U.S.A for packages 2, 3, & 4 (SC-2) and the value of consultancy services is Rs.15.59 crores.