![]()
|
||||
|
GOVERNMENT OF TAMIL NADU
CONSULTING ENGINEERING SERVICES INDIA PVT.LTD, No 49, SOUTH BEACH AVENUE, MRC NAGAR, CHENNAI-28
|
||||
|
contents |
||||
| GLOSSARY OF R&R
TERMS 4 |
4 | |||
| EXECUTIVE
SUMMARY 8 |
8 | |||
| 1.0:
INTRODUCTION 10 |
10 | |||
| 2.0: LAND
ACQUISITION AND RESETTLEMENT IMPACTS 15 |
15 | |||
| 3.0: BASELINE
SOCIO-ECONOMIC CHARACTERISTICS 17 |
17 | |||
| 4.0:
IMPLEMENTATION ACTIVITIES 19 |
19 | |||
|
T A B L E S
|
||||
| Table 1.1: Details of PAH s
villagewise Table 1.2: Details of Land to be acquired Table 1.3: Evaluation of Alternative Alignment Options Table 2.1: Type of Land Involved Table 4.1: Implementation Schedule for RAP Table 4.2: Monitory Indicators for Physical Progress Table 4.3: Monitory Indicators for Financial Progress Table 4.4: Indicators for Impact evaluation Table 4.5: Summary of R&R Budget |
11 12 13 15 19 21 22 24 27 |
|||
|
ANNEXURES
|
||||
|
Annexure 1 : Minutes of Public Consultation
Meeting |
||||
|
GLOSSARY OF R&R TERMS
Assistance
Corridor of Impact
(CoI)
|
||||
|
EXECUTIVE SUMMARY |
||||
|
The Government of Tamil Nadu (GoTN) has undertaken the Tamil Nadu Road Sector Project (TNRSP) for implementing this project with World Bank (WB) loan assistance. M/s Consulting Engineering Services (I) Pvt Ltd has been appointed for assisting the PIU (Project Implementing Unit) in the preparation of RAP for this project. This RAP has been prepared for Kumbakonam Bypass Extension only, based on the outputs of feasibility studies for the formation of a road length of 4.080 Km. The Resettlement Action Plan (RAP) for Kumbakonam Bypass Extension under Tamil Nadu Road Sector Project (TNRSP) contains the magnitude of Land Acquisition and mitigation of impacts. This report also includes the baseline socio-economic characteristics of the Project Affected households (PAHs), R&R policy provisions, entitlements, outcomes of the consultations held with the communities, implementation and monitoring mechanisms, budget and implementation of the R&R provisions. Minimum acquisition of land and minimum disturbance to the existing features are the prime objectives of the design. Socially sensitive stretches have been avoided by means of detailed study of different alternative alignments. Minimization of impacts within the limitations of technical requirements and cost effectiveness were emphasized. To address the resettlement issues in the project, the GoTN has adopted a Resettlement and Rehabilitation Policy for the project (vide GO.Ms.No.193 dated 10.08.1998). The RAP has been prepared as per the provisions laid down in this policy. The entitlements and options for each impact category have been provided in the detailed entitlement matrix. This matrix has been formed the basis for formulation of entitlement options and enabled the working out of the R&R budget for the project. Due to the project, totally 199 households are getting affected by losing land or structures, land and structures. Out of them 184 PAHs are losing land only, 5 PAHs are losing structure only, 10 PAHs are losing land and structure. On the title holders who lose their structures, resettlement sites for 11 Nos of PAHs are required as they have opted for alternative houses. These PAHs will be allotted each a house in the resettlement sites with necessary infrastructure facilities. During the Public Consultation meeting, they have been apprised of the option of the alternative houses, as per the Entitlement Matrix. Total land requirement in the project is 11.1747 Ha. Out of which 7.0905 Ha from private landowners, 0.3233 Ha of Trust land, 1.9016 Ha of Temple land and 1.8593 Ha of Government land will be acquired. Only the lands of Temples and Trusts are affected and no temples are affected. The temple and trust authorities are eligible for compensation only. The proposed project has no impact on Tribal population and there is no loss of community resources, also. The proposed alignment was finalized based on the concerns and responses of likely PAPs, individual consultations with the PAPs during the census surveys, public meeting held with the local communities involving PAPs and Government agencies to minimize the adverse impacts. There was over- whelming response from the public who welcomed the proposal to construct the bypass and 100% of the people are in favor of the bypass. The socio-economic conditions of the PAHs are furnished as follows. v Income Level The income of the various groups reveal that 15% of the PAHs fall in the group of below poverty line, 32% between Rs.2103/- to Rs.3000/- p.m., 19% between Rs.3001/- to Rs.5000 p.m, 32% between Rs.5001/- to Rs.15000 p.m and 2% above Rs.15001 p.m. v Occupation Profile of PAHs & Family members The occupation profile of the PAHs & Family members reveals that Agriculture is the predominant activity with 11% highest among the PAHs engaged in Cultivation and the remaining are involved as Agriculture labors (4%), Casual labors (2%), Private sector salaried (4%), Government sector salaried (4%), Business (4%), Unemployed (11%) and Not in Work force (60%). v Religion By religion, majority of the PAHs are Hindus (97%) followed by the Muslims (2%) and Christians (1%). v Literacy of PAHs & Family members 66% of the PAPs are Literates and 29% are Illiterates and the others are children (5%). Out of the total PAHs & Family members, 7% belong to Primary education, 10% has carried out their Middle school education, 20% has completed High school education, 12% has completed Higher Secondary education, the remaining 18% have carried out College education. v Age-group Classification of PAHs & Family membersAs per socio economic survey carried out, the elderly population (i.e.) 60 & more than 60 years accounts for 12% and the remaining 88%, fall within the age group of 60 and below.v Vulnerable populations In total there are 28% are vulnerable and 72% are non vulnerable. It is observed that there are 19% are Schedule caste, 6 % are PAHs below Poverty line, 2 % of the PAHs are of elderly population and 1% is Woman- headed. Since all the PAHs are Title- Holders, they are eligible for compensation only or alternative houses in case of loss of structures.
A Social
Development Unit (SDU) has been set up within the PIU to tackle land
acquisition. An officer of the rank of Joint Project Director (JPD) has
been entrusted the responsibility to oversee and co-ordinate the
implementation activities related to Land Acquisition. Elaborate
mechanisms are proposed to assist the JPD, both at the head quarters as
well as at the field level to ensure effective implementation of the
project. The State and District Level Committees have been constituted to
redress the grievances of the PAPs. v R & R Costs and Budget: The budget for the implementation of the project and other associated costs has been estimated as INR 27.00 million.
|
||||
1. 0 INTRODUCTION
|
||||
|
1.1 The Resettlement Action Plan (RAP) for the Tamil Nadu Road Sector Project (TNRSP) contains the magnitude of Land Acquisition and the mitigation of impacts. This report also includes the baseline socio-economic characteristics of the Project Affected House holds (PAHs), R&R policy provisions and entitlements, outcomes of the consultations held with the communities and the budget for the implementing the project. 1.2 The Kumbakonam bypass extension likely to be implemented in the second phase of the project, under the contract package TNRSP-05. The length of the corridor for this package is 4.080 Km. The road will be formed with a total road width of 12.0 m, as Two Lane Gravel Shoulders (2 LGS). The riding surface will be of 2 Lanes, with a width of 7.0 m (2x3.5). The road will have Gravel shoulders on both sides and the total width of the shoulders alone will be of 5.0 m (2x2.5) 1.3 The social impact assessment and resettlement planning carried out as part of the project preparation which involves the following five main elements: · Screening and social impact assessment as a part of project feasibility study; · Preparation of Resettlement and Rehabilitation Entitlements and policy framework; · Census of the potentially affected population; · Public consultation; and, · Preparation of Resettlement Action Plan (RAP).
1.4 The objective of the RAP is to improve the overall living standards of the persons affected due to the project. This will be achieved by adopting the following measures. · Minimisation of land acquisition and resettlement impacts, reduction of the CoI and adopting constricted cross-sections; · To provide compensation to PAPs for the loss of assets under private negotiation process or under Tamil Nadu High Way Act. 2001. · To present an action plan for the disbursement of compensation and assistance prior to commencement of civil works.
1.5 The total land requirement for Kumbakonam Bypass Extension to be constructed for TNRSP is 11.1747 hectares, according to the approved alignment. The exact magnitude of social impacts and land acquisition will be worked out through a Resettlement Action Plan (RAP). Based on the approved alignment, broad R&R budget estimate has been provided in the overall R&R budget. 1.6 The loss of assets involves impacts on Agriculture land and structures as Major& Minor impacts. The following Table reveals the details of impacts such as loss of land only, loss of land & Structure.
1.7 The area
of the land required for the project is totally 11.1747 hectares.
The break-up details are furnished as follows. |
||||
|
Table 1.1 Details of PAHs (Village-wise) |
||||
|
ABSTRACT: PAHs, TRUSTS AND TEMPLES |
||||||||||
| S.No. | Name of the Village | No. of PAHs who lose land only | No. of PAHs who lose structure only | No. of PAHs who lose land & Structure Total | No. of PAHs | Major PAHs | Minor PAHs | No. of Trusts | No. of Temples | Total No. of Land and Structure Owners Affected |
| 1 | Ullur | 11 | 0 | 0 | 11 | 1 | 10 | 1 | 0 | 12 |
| 2 | Thepperumanallur | 73 | 0 | 3 | 76 | 7 | 69 | 0 | 1 | 77 |
| 3 | Palavattankattalai | 14 | 1 | 0 | 15 | 3 | 12 | 1 | 1 | 17 |
| 4 | Srinivasanallur | 41 | 1 | 2 | 44 | 4 | 40 | 1 | 1 | 46 |
| 5 | Krishnapuram | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 1 |
| 6 | Sivapuram | 4 | 0 | 0 | 4 | 2 | 2 | 1 | 1 | 6 |
| 7 | Malayappanallur | 36 | 1 | 3 | 40 | 14 | 26 | 1 | 1 | 42 |
| 8 | Karuppur | 5 | 2 | 2 | 9 | 9 | 0 | 0 | 0 | 9 |
|
TOTAL |
184 | 5 | 10 | 199 | 40 | 159 | 5 | 6 | 210 | |
|
1. Area of Private land = 7.0905 Ha 2. Area of Trust land = 0.3233 Ha 3. Area of Temple land = 1.9016Ha 4. Area of Govt. land = 1.8593 Ha Total area of the land required = 11.1747 Ha The Break-up details of land to be acquired from private landowners, Temples & Trusts, village-wise are furnished in the following Table. TABLE1.2: Details of Land to be acquired (Village-Wise) |
|
ABSTRACT: LAND DETAILS |
||||||||||||
S.No |
Name of the Village | Type of Land | Major / Minor | Nature of Land | Total | Government land | Grand Total | |||||
| Private land | Trust land | Temple land | Major | Minor | Irrigated | Un irrigated | Residential | |||||
| 1 | Ullur | 0.0678 | 0.0000 | 0.0000 | 0.0450 | 0.0228 | 0.0450 | 0.0000 | 0.0228 | 0.0678 | 0.3265 | 0.3943 |
| 2 | Thepperumanallur | 1.9240 | 0.0000 | 0.1450 | 0.8745 | 1.1945 | 0.2745 | 0.6000 | 1.1945 | 2.0690 | 0.3390 | 2.4080 |
| 3 | Palavattankattalai | 1.5660 | 0.0500 | 0.4200 | 0.7450 | 1.2910 | 0.8460 | 0.5450 | 0.6450 | 2.0360 | 0.1354 | 2.1714 |
| 4 | Srinivasanallur | 1.7908 | 0.0000 | 0.4419 | 0.8789 | 1.3538 | 0.2509 | 0.6280 | 1.3538 | 2.2327 | 0.4418 | 2.6745 |
| 5 | Krishnapuram | 0.0000 | 0.0000 | 0.5939 | 0.5789 | 0.0150 | 0.0000 | 0.5939 | 0.0000 | 0.5939 | 0.1895 | 0.7834 |
| 6 | Sivapuram | 0.1931 | 0.0150 | 0.2750 | 0.3756 | 0.1075 | 0.1350 | 0.3481 | 0.0000 | 0.4831 | 0.1638 | 0.6469 |
| 7 | Malayappanallur | 0.9084 | 0.2583 | 0.0258 | 1.1442 | 0.0483 | 0.7855 | 0.3587 | 0.0483 | 1.1925 | 0.0000 | 1.1925 |
| 8 | Karuppur | 0.6404 | 0.0000 | 0.0000 | 0.6404 | 0.0000 | 0.4512 | 0.1892 | 0.0000 | 0.6404 | 0.2633 | 0.9037 |
|
TOTAL |
7.0905 | 0.3233 | 1.9016 | 5.2825 | 4.0329 | 2.7881 | 3.2629 | 3.2644 | 9.3154 | 1.8593 | 11.1747 | |
1.8 The implementation of the formation of Kumbakonam Bypass Extension is to be carried out and the contractor is to be selected for the execution. Road construction activities will be generally confined to 12 months. 1.9 The PIU, through the District Collector has to initiate the LA process. The LA will be completed prior to the start of construction by the contractor for the entire stretch, and the compensation and assistance for land will be disbursed as per entitlement provisions of R&R policy. 1.10 In order to arrive at the best alternative, two different feasible options of alignments have been studied. Each alignment has its own merits and de-merits. An effort has been made to find out the best of two, by collecting more details along these alignments. The feasibility evaluation of the alternate alignments is presented in Table 1.3 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Table 1.3 Evaluations of Alternate
Alignment Options |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Note: * The normal Right of Way proposed is 27 metres. In high embankments like approaches to ROBs and approaches to high level bridges, it is likely to be more. 1.11 From the above table it may be seen that the Alternative-I, impacts 2 ponds, 55 structures, 5 temples and a school building also, whereas the Alternative-II does not affect as much. Moreover Alternative-I, is very close to the town and the development potential is higher and only for this reason many houses (55 Nos) are affected. In total, the cost of Alternative-II is lesser than the Alternative-I and hence Alternative-II has been chosen as the better alignment. In addition to that, majority of the people have also opted for Alternative –II only, during the Public Consultation Meeting and the minutes of Meeting are enclosed in Annexure – 1. 1.12 So, the Alternative II is the best option for the bypass of Kumbakonam town, in terms of Environmental & Social impacts and also from engineering point of view. Therefore, Alternative II is selected and the Detailed Engineering has been carried out for this option. 1.13 In continuation of the Draft RAP, another Consultation Meeting has also been conducted for the Project Affected Households & People, for explaining the Compensation for the individuals, R& R Policies and the Entitlement Matrix of the Government of TamilNadu guided by the World Bank. The minutes of the consultation meeting with PAPs & PAHs are enclosed in Annexure 1 A. 2. 0 LAND ACQUISITION AND RESETTLEMENT IMPACTS2.1 This chapter outlines the magnitude and extent of the various impact categories. These shall form a base for working out the R& R budget, in accordance with the provisions of the Entitlement Matrix. 2.2 The project involves land for acquisition for formation of bypass. Altogether 11.1747 Ha of land will be acquired for the project, out of which 9.3154 Ha of patta land will be acquired from private owners and the balance of 1. 8593 Ha land belongs to Government. The details of irrigated and un–irrigated land are provided as follows in Table 2.1. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
2.3 There are cases of severance of land, especially along the bypass. The PAPs whose land will be severed have been identified based on the Land Plan Schedules (LPS). The entitlement framework for the project provides an additional of 25% of the total compensation as severance allowance, to compensate for the severance impacts. 2.4 Out of the 199 PAHs in the project, 40 PAHs are subjected to major impact and 159 PAHs are subjected to minor impact. 2.5 The compensation for the land to be acquired will be paid through private negotiation with the concerned landowners. The fixing of compensation will involve the following steps. · The concerned Thasildhar will carry out a scrutiny of land prices (based on guideline values Dated, August 1st 2007). · The District Level Committee under the chairmanship of the District Collector will carryout negotiations with the individual landowners based on the guideline value. In order to represent the real replacement cost towards the payment of compensation, the negotiated compensation shall not be less than 150% of the guideline value of the Registration department. · In the event of dissatisfaction over the value with the negotiation committee, the landowner has the option of representing his case to the State Level Committee. · The, guideline values as updated by the GoTN on August 1st, 2007 have been adopted for the project. To update guidelines values for more than one year old on the date of negotiation, an increase of 5% per annum will be paid. In addition to this, an additional amount of 9% will be paid to meet out the cost of registration and stamp duty irrespective of whether the PAP repurchases the lost asset or not. · Tree Value: For any trees attached to the land to be acquired, the value of fruit bearing trees will be estimated by the Additional Director (AD), Horticulture and Timber trees will be estimated by the Divisional Forest Officer (DFO). 3.0 Baseline Socio –Economic Characteristics3.1 This chapter presents the socio- economic features of the project and an analysis of baseline socio-economic characteristics of the Project Affected Persons (PAPs). 3.2 The key baseline socio-economic characteristics have been worked out based on analysis of the census survey data. The indicators worked out include those related to income, occupation, etc. 3.3 Structured formats were prepared on which the data was recorded separately for the household records, information collected included inventory of assets loss, ownership profile, household information, etc. In general, information on demographic and social characteristics including caste, tribe, income level, gender of head of household etc. were collected to determine the vulnerability of the project affected persons. 3.4 The PAH suffering the following impacts are categorized as Major impact: · Loss of place of dwelling · Loss of place of business · Loss of livelihood · Loss of 25% or more of agriculturally productive land out of the affected land holding, or · Loss of land due to severance on acquisition and the remaining land is not economically viable 3.5 All the PAHs available on the date of joint verification will be eligible for entitlements in accordance with the R& R policy provisions. The list of entitled persons will be made available for verification in the office of the Divisional Engineer (Highway) TNRSP, Kumbakonam 3.6 Any further encroachment into the CoI will be prevented through regular monitoring by the Divisional Engineer of the project in co-ordination with the Regular Divisional Engineer. (Highways) The demographic and socio-economic profiles are given as follows: 3.7 Income Level The income of the various groups reveal that 15% of the PAHs fall in the group of below poverty line, 32% between Rs.2103/- to Rs.3000/- p.m., 19% between Rs.3001/- to Rs.5000 p.m, 32% between Rs.5001/- to Rs.15000 p.m and 2% above Rs.15000 p.m. The profile by village wise is presented in Annexure - 9. 3.8 Occupation Profile of PAHs & Family members The occupation profile of the PAHs & Family members reveals that Agriculture is the predominant activity with 11% amongst the PAPs engaged in Cultivation and the remaining are involved as Agriculture labors (4%), Casual labors (2%), Private sector salaried (4%), Government sector salaried (4%), Business (4%), Unemployed (11%) and Not in Work force (60%). The occupation profile of the PAHs is presented in Annexure -10. 3.9 Religion By religion, majority of the PAHs are Hindus (97%) followed by the Christians (1%) and Muslims (2%). The profile of the religion by village-wise is presented in Annexure -11.
3.10 Literacy of PAHs & Family members 66% of the PAPs are Literates and 29% are Illiterates and the others are children (5%). Out of the total PAHs & Family members, 7% belong to Primary education, 10% has carried out their Middle school education, 20% has completed High school education, 12% has completed Higher Secondary education, the remaining 18% have carried out College education. The profile of literacy by village-wise is presented in Annexure - 12.
3.11 Age-group Classification of PAHs & Family membersAs per socio economic survey carried out, the elderly population (i.e.) 60 & more than 60 years accounts for 12% and the remaining 88%, fall within the age group of below 60 years. The profile by village-wise is presented in Annexure – 13.3.12 Vulnerable populations In total there are 28% are vulnerable and 72% are non vulnerable. It is observed that there are 19% are Schedule caste, 6 % are PAHs below Poverty line, 2 % of the PAHs are of elderly population and 1% are Woman- headed. Since all the PAHs are Title- Holders, they are eligible for compensation only. . The profile of the vulnerable population by village wise is furnished in the Annexure -14. 3.13 Profile of PAHs: The census of the landowners impacted have been carried out, the profile of the PAPs has been presented in the Annexures 15.1 – 15.8. 4.0 IMPLEMENTATION ACTIVITIES 4.1 The activities considered to be undertaken in the implementation of RAP are with necessary sequencing of the activities. There will be scope for updating the schedule during the progress of the implementation. The site will be handed over to the contractor for commencing civil works free, after acquiring the land and after distribution of compensation and allowances. Speedy efforts will be taken to hand over the lands involved in the acquisition process quickly after fulfilling the statutory requirements prescribed there in. The implementation scheduled is presented in Table 4.1, as follows
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Table 4.1 Implementation Schedule for RAP |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
4.2 4.2 The RAP document is to be disclosed for public access and will be made available in the following places in addition to the PIU. · District library at Thanjavur · TNRSP web site: www.tnrsp.com · In the Panchayat offices of all concerned villages
4.3.
To provide information on the fixation of negotiation prices for land
acquisition in the project and to explain the various entitlement options in
the project, brochures are to be prepared in Tamil and will be available to
all PAPs prior to negotiations. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Table 4.2 Monitoring Indicators for Physical Progress |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
4.9 Internal monitoring will track the physical and financial indicators as mentioned in Table 4.2 and 4.3 Monitoring will be carried out by the SDU of the PIU. Monthly Progress report shall be prepared and submitted to the PIU at Head Quarters reporting actual achievements against the targets fixed with reasons for shortfalls, if any. 4.10 All monitoring reports will have to be compiled within fifteen days at the end of each month by the PIU at the field level. The filled up formats will be compiled, analyzed and results will be submitted to the Project Director for the assessment on the monthly progress of implementation of the RAP. 4.11 The main objectives of the Impact Evaluation to be carried out (If necessary), have been mentioned below: · To assess whether the PAPs have improved their living standards, in terms of income, ownership of land. · To monitor the schedules and achievement of targets; and · To evaluate whether the outcomes of social development objectives of the project are being achieved. 4.12 All the PAPs who have spent more than 6 months after receiving compensation will be considered for the impact evaluation. Any problems encountered will be assessed and necessary changes will be recommended to the PIU for consideration. The impact evaluation will emphasize on the assessment of achievements of the project targets and the change in quality of life of the PAPs. Necessary evaluation indicators will be developed for carrying out the evaluation assignment. All the evaluations are expected to be done on the basis of selective indicators. After the implementation of the project, an agency will carry out an end-term evaluation to assess the effectiveness of the implementation of the R&R provisions. 4.13 The impact evaluation will be made on the issues as mentioned below: · Restoration of income levels of the PAPs; · Changes and shifts in occupational pattern; 1.14 As standard format with indicators for impact evaluation has been presented in Table 4.4 below: Table 4.4 Indicators for Impact Evaluation |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
4.16 The cost for implementation of RAP has been worked out in accordance with R&R policy approved by GoTN and based on the information from socio-economic survey data. The property owners subject to minor impacts will be provided only compensation for loss of their properties. Other assistances as per the R&R Policy provisions will be provided for the PAHs having major impact due to the project. 4.17 The following Table presents the overall budget with costs for all R&R components for Kumbakonam Bypass Extension. 4.18 The total budget for compensation for Land including cost for trees are calculated based on the guideline value in the year 2007-2008. The summary of R&R budget is given in the Table 4.5 Table 4.5 Summary of R&R Budget |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(Or) Rupees 27.00 Millions |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
ANNEXURES [1-15] |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Annexure - 1 (MINUTES OF THE PUBLIC CONSULTATION MEETING) TAMIL NADU ROAD SECTOR PROJECT Chairman: Divisional Engineer, TNRSP, Kumbakonam Venue: Muthupillai Mandapam Middle School, Pazhavattan kattalai, Kumbakonam Date: 19th January, 2008 Time: 10:00 am A public consultation meeting has been held for the proposed bypass extension for Kumbakonam town, linking (1) Kumbakonam – Myladuthurai road (SH), (2) Kumbakonam – Karaikal road (SH) and (3) Kumbakonam – Thiruvarur road (SH). The link between Kumbakonam – Thanjavur road (SH) and Kumbakonam – Chennai road (SH) already exist. The meeting was held under the chairmanship of the Divisional Engineer (TNRSP) Kumbakonam. Government officials, People’s representatives, Panchayat union presidents, Traders, Representatives of Non Government Organizations and about 55 Nos of Project Affected People have participated the meeting. The Address of the Resettlement Officer, Tamil Nadu Road Sector Project, Chennai The Resettlement Officer, Tamil Nadu Road Sector Project, Chennai welcomed the gathering and briefly explained the project features. Then the Chairman addressed the gathering, explained the necessity of the bypass extension and requested the participants to share their views and opinions regarding bypass.The Address of Mr. N. Viswanathan, M& E Consultant Mr. N. Viswanathan , M& E Consultant welcomed the proposal of the bypass, as the Consultants proposed various alternatives, which is a long felt need of the public in the developments like, good access of traffic, reducing the congestion to the Central part of Kumbakonam town, avoiding enormous delay in crossing the town. He readily agreed and assured to extend full support in offering necessary guidance in the process to be followed for the acquisition of the required land for the proposed project. He explained them about the entitlement matrix to the public. The Address of Mr. L.G Balakrishanan, Highway Engineer, CES (I) Pvt Ltd He explained the World Bank norms and guidelines related to this project. He also explained technically about the two alternatives with merits and demerits and he explained that proper compensation for the affected land, structures & trees (etc) will be paid. In view of the positive impacts of the project, like development of industries and trades, he requested the public, to give their co-operation without considering the unavoidable impacts on the land and others. Interactions with Public: The client and consultants have interacted with the public, invited their views, explained them briefly and clarified their queries up to their satisfaction. The Views of the Public The members and the pubic participated in the meeting; have accepted the bypass proposal and wanted to commence the works at the earliest and also opted for Alternative – II Table: Project responses to the issues raised in the Public Consultation Meeting Location: Muthupillai Mandapam Middle School, Pazhavattan kattalai, Kumbakonam
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The Divisional Engineer (H) TNRSP explained that the project would be implemented and carried out as per the norms and guidelines of the World Bank. The loan assistance for the proposed bypass from the World Bank will be helpful to the Government of Tamil Nadu in construction of the bypass and it will be useful to the public to avoid the delay in transport, to avoid traffic congestion, to give smooth flow of traffic and to improve the infrastructures on both sides of the road. The Divisional Engineer explained them about the compensation provisions as per the World Bank’s guidelines for the affected land, trees structures etc. He also touched upon the process of replacement of Common Property Resources (CPRs) during implementation of the project like Temples, School buildings; etc (If any). In view of the positive impacts of the proposed bypass, like development of industries and trades, the Divisional Engineer has requested the public to extend their full co-operation & participation to make the project success. Outcome: There was over- whelming response from the public who welcomed the proposal to construct the bypass and 100% of the people are in favor of the bypass. In that 62 % of the public are in the favor of the Alternative - 2 and 38 % of the public are in favour of any kind of alternatives and nobody is un-willing for the bypass proposal. Conclusion: There was an overwhelming response from the public who welcomed the proposal to construct a bypass. The meeting concluded with a vote of thanks from the consultants, M/s.Consulting Engineering Services (India) Pvt Ltd, Chennai – 600 02 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Annexure – 1A (MINUTES OF THE CONSULTATION MEETING WITH PAHs & PAPs) TAMIL NADU ROAD SECTOR PROJECT Chairman: Revenue Divisional Officer, Kumbakonam Venue: Muthupillai Mandapam Middle School, Pazhavattan kattalai, Kumbakonam Date: 02nd November, 2008 Time: 10.30 am A consultation meeting with PAPs & PAHs has been held for the proposed bypass extension for Kumbakonam town for explaining compensation & R&R policies of this project. The meeting was held under the chairmanship of the Revenue Divisional Officer, Kumbakonam. The Deputy Collector, TNRSP, Chennai, The Divisional Engineer (TNRSP) Kumbakonam, The Special Tasildhar, TNRSP, Thanjavur, The Tasildhars, Kumbakonam & Tiruvidaimarudhur, Surveyors, Village Administrative Officers and Government officials, People’s representatives, Panchayat union presidents, Non Government Organizations and Journalist and PAPs & PAHs have participated the meeting. The Address of the Deputy Collector, Tamil Nadu Road Sector Project, Chennai The Deputy Collector, Tamil nadu road sector project, Chennai welcomed the gathering and welcomed the proposal of the bypass, as the Consultants proposed various alternatives, which is a long felt need of the public in the developments like, good access of traffic, reducing the congestion to the Central part of Kumbakonam town, avoiding enormous delay in crossing the town briefly explained the R&R policies and compensation of the guideline values for the project affected people and house holds.The Address of Divisional Engineer, TNRSP, Kumbakonam The Divisional Engineer explained the process to be followed for the acquisition of the required land and structures for the proposed project. He explained them about the various benefits to the project affected households and people as per the entitlement matrix. He also explained the about the resettlement sites and alternative houses to the beneficiary and compensation for the individuals. He also explained that the complete details of the Resettlement Action Plan of this project are available in the district library, Panchayat offices, Divisional office and also in the web site. The Address of Mr. L.G Balakrishanan, CES (I) Pvt Ltd He also explained technically about the alignment and proper compensation for the affected land, structures & trees (etc) and supported in giving the necessary details regarding the alignment for the enquires made by the PAHs. Interactions with Public: The delegates at the Dias with help of the Surveyors and VAO and consultants have interacted with the public, explained in detailed and clarified the queries about the compensation and other benefits. Annexure - 2 Tamil Nadu HW Act, 2001 (Extracts)
[No.626] TAMIL NADU HIGHWAYS ACT, 2001 (Extracts from Tamil Nadu Highways Act, 2001) Chapter II Declaration of Highways, Highways Authorities and their Powers and Functions 5 (2) The Divisional Engineer, Highways Department of the Government in-charge of each division, shall be the Highways authority for that division. Chapter IV Acquisition of Property 15 (1) If the Government are satisfied that any land is required for the purpose of any highway or for construction of bridges, culverts, causeways or other structures thereon or for any purpose incidental or ancillary thereto, in furtherance of the objects of this Act, they may acquire such land by publishing in the Tamil Nadu Government Gazette a notice specifying the description of such land and the particular purpose for which such land is required. (2)Before publishing a notice under sub-section (1), the Government shall call upon the owner and any other person having interest in such land to show cause within such time as may be specified in the notice, why the land should not be acquired. The Government shall also cause a public notice to be given in such manner as may be prescribed. 18. Every owner or person interested in any land acquired under this Act shall be entitled to receive and be paid an amount as hereinafter provided. 19 (3) Where no such agreement can be reached, the Government shall refer the case to the Collector for determination of the amount to be paid for such acquisition as also the person or persons to whom such amount shall be paid. Provided that no amount exceeding such amount as the Government may, by general or special order, specify, to be paid for such acquisition shall be determined by the Collector without the previous approval of the Government or such officer as the Government may appoint in this behalf. 23. Where any amount has been deposited in court under sub-section (3) of section 22, the Court may either of its own motion or on the application made by or on behalf of any party interested or claiming to be interested in such amount, order the same to be invested in such Government or other securities approved by the Government as it may think proper, and may direct the interest or other proceeds of any such investment to be accumulated and paid in such manner as will, in its opinion, give the parties interested therein the same benefit there from as they might have had from the land in respect whereof such amount has been deposited or as near thereto as may be. 24. When the amount is not paid or deposited on or before taking possession of the land, the Government shall pay the amount determined with interest thereon at the rate of nine per cent per annum from the time of so taking possession until it shall have been so paid or deposited. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
ANNEXURE 3 VARIOUS STAGES FOR THE DETERMINATION OF COMPENSATION AND GOs The various stages of the determination of compensation are given as follows Ø By an agreement between the land owner and the District Collector. Ø By fixing the land value under section 19(3) of Tamil Nadu Highway Act 2001 by following the procedures under section 23 & 24 of the Land Acquisition Act, 1894. Ø Any person aggrieved by the decision of the Collector or any other officer, may within 60 days require the matter to be referred to the court as provided under section 18 of the Land Acquisition Act 1894. Ø However, as an alternative to the acquisition under the TNHW Act 2001, Government issued orders dated, 25.02.2003, that 150% of the guideline value (minimum) should be given as compensation by private negotiations under an agreement between the land owner and the District Collector. (District Level Negotiation Committee). Ø In case the use of TN Highway Act, the compensation will be paid prior to taking over the land for those who are re-available and in case those who are not available, it will be deposited in the court. The basic data required for the Social Assessment for implementing the R&R related activities for the project are given as follows Ø Profile of PAPs: The project should provide adequate information on settlements, population and households impacted. Ø Livelihood Sources: The project should provide information about the occupational pattern of the affected population along with average household income per annum. Ø Employment in the Project: The project should make necessary arrangement for creating employment opportunities during the construction period for the local people. The subject and reference of various G.Os relating to R&R for the project are given as follows · Authorization of District Collectors to initiate land acquisition through private negotiation (G.O. Ms.No.174 dated 25.09.2001): This G.O. authorizes the district collectors of the 11 districts along the TNRSP roads to initiate the land acquisition proceedings through private negotiation, on behalf of the project · Tamil Nadu Road Sector Project – Implementation – Committees Constituted – Orders Issued (G.O.Ms.N.221 dated 19.12.2000): To achieve the objectives of the R&R policy framework of TNRSP and to accelerate the speedy implementation of the project. · Land Acquisition – TNRSP – Relaxing Conditions for Acquisition of Wetlands – Orders Issued (G.O.Ms.No.151 dated 07.09.2001). As per the conditions prescribed in G.O.Ms.No.363, Revenue Department, dated 28.04.95, acquisition of wetlands further purposes is not permitted. After careful examination, it was inferred that this acquisition was unavoidable, after which condition for wetlands acquisition has been relaxed for this project as a special case through G.O.Ms.No.151 dated 07.09.2001. · Government Order on Sanction of Rs.49.5 Crore towards Land Acquisition (G.O.Ms.No.59 dated 16.03.2001): This G.O. provides an administrative sanction for a sum of Rs.49.5 crore to compensate the PAPs towards acquisition of 805 ha of land (in total for the whole project TNRSP 01-05) in accordance with the provisions of the R&R policy, by negotiations with the landowners. · Government Order on Enhanced Payment of compensation through private negotiation (G.O.Ms.No.40 dated 25.02.2003): This G.O. authorizes the District Collectors of 11 districts where the TNRSP is being implemented to fix up land value not less than 150% of the Guideline Value at the time of private negotiations with the landowners. · Government Order on constituting a policy framework approved empowered committee (G.O. Ms.No.184 dated 16.10.2002): This G.O. provides for a constitution of an empowered committee to provide immediate guidance and approval of issues during project implementation that are beyond the powers of the project authority. · Government Order on creation of Special Revenue Staff (G.O.Ms.No.174 dated 15.07.1998): This G.O. provides with the sanction of creating Special Revenue Staff experienced in environmental and land acquisition issues, who will help and coordinate land acquisition activities for the project. · Government Order on sanction of constituting R&R Cell (G.O.Ms.No.20 dated 30.01.2003): This G.O. accords sanction for constituting R&R Cell for the project that will oversee land acquisition and implementation of the Resettlement Action Plan. · The Government Order on Amendment of Entitlement Matrix regarding Land Purchase Grant and House Construction Grant G.O. (Ms.) No.264 dated 13.12.2006 provides amendment to Land Purchase Grant and House Construction Grant of the Entitlement Matrix. Land purchase grant at 25% of total compensation will be available to those PAP’s who lose more than 25% of their land holding in the village and are left with less than minimum economic land holding (less than 1 hectare of irrigated or 2 hectares of un irrigated or equivalent in that village. (The G.O. is enclosed for reference as Annexure.4) · The GoTN, in accordance with the principles laid down in the Operational Directives of the World Bank and the policies of the GoI, has prepared the R&R policy for TNRSP. The Highways Department in G.O.Ms.No.193, dated 10.08.1998 accepted these principles and Policy Framework as the basis for the RAP. This RAP document has been prepared as per the policy described in the above G.Os. · Principles of the Policy on Mitigation of Impacts: It is an integral policy of the project to mitigate all the impacts to the extent possible and where this is not possible; PAPs will be compensated and assisted. The principles of R&R policy are that: Ø Involuntary resettlement shall be avoided to the extent possible or minimized where ever feasible, exploring all viable alternative project designs. Ø Where displacement is unavoidable, people losing assets, livelihood or other resources shall be assisted in improving or at a minimum regaining their former status of living at no cost to themselves. Ø People’s participation shall be undertaken in planning and implementation of the project. Type of Impacts to be addressed There are three broad categories of social and economic impacts, which require mitigation in this project. They include: § Loss of assets, namely lands and assets, § Loss of livelihood or income opportunities, and, § Collective impacts on groups, such as loss of Common Property Resources.(not for this project) The first two categories represent direct project impacts on an identified population. Here, the affected people will be surveyed and registered. The third category represents an indirect impact, where group members need not be individually registered. · Entitlement Framework: The entitlement framework for this project has been prepared following the R&R Policy. The entitlements have been decided, as part of the mitigation measures to compensate the losses to the PAPs. The definitions regarding entitlements and the eligibility Criteria are presented as a separate section, Glossary of R&R terms. A summary entitlement matrix is provided in Annexure.4 Annexure 4 Detailed Entitlement Matrix The detailed entitlement matrix for the project is presented below: |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
In addition to the entitlements to all affected PAHs / PAPs, the following additional provisions will be given to the vulnerable PAHs / PAPs:· Land purchase grant @ 25% of the total compensation received to vulnerable PAHs losing land; · An option of an alternative built house or shop at 1/3rd cost for vulnerable titleholder PAHs; · An alternative built house free of cost for vulnerable residential squatters; · An alternative built shops free of cost or an employment generation asset up to Rs.30,000/- for vulnerable squatters losing shops; · Subsistence allowance for six months for vulnerable people; and · Training for self-employment opportunities to all adult members for vulnerable Squatters |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Annexure - 5
GO (Ms) 264,
dated 13.12.2006 Highway Department – Tamil Nadu Road Sector Project – Resettlement Action Plan Volume I Entitlement Matrix – Amendment to Table 3.3 Issued Highways (HF 2) Department G.O. (Ms) No.264 Dated: 13.12.2006 Read:- 1. G.O.(Ms.) No.184 Highways (HF 1) Department, dated 16.10.2002 2. G.O. (Ms).No.74, Highways (HF 1) Department, dated 8.4.2003 3. G.O. (Ms).No.168, Highways (HF 1) Department, dated 11.09.2006 4. From the Project Director, Tamil Nadu Road Sector Project, Project, Letter No.1372/2005/R3, dated 27.06.2006 ***** ORDER:- 1. In the order second read above the Government have accorded approval for the Resettlement Action Plan (RAP) and Resettlement and Rehabilitation measures. 2. In the order 3rd read above the Government have issued amendment or Income Generation Assets in Table 3.3 in the Detailed Entitlement Matrix with the direction that regarding Land Purchase Grant and House Construction Grant, orders will be issued separately. 3. In this letter fourth read above the Project Director, Tamil Nadu Road Sector Project has sent proposals to Government for issue of necessary amendment in respect of Entitlement Matrix Table 3.3 regarding Land Purchase Grant and House Construction Grant based on the suggestion of the World Bank as communicated in their side memoire of 2005 and requested for orders. 4. The Government after careful consideration accepts the proposal of the Project Director, Tamil Nadu Road Sector Project and accordingly issue the following amendment to table 3.3 in Detailed Entitlement Matrix. 5. This order issues with the concurrence of the Finance Department vide its U.O.No.284/SS (KPC) 06, dated 08.12.2006. Amendment to Table No.3.3 in Entitlement Matrix
(BY ORDER OF THE GOVERNOR) K. ALLAUDIN SECRETARY TO GOVERNMENT |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The Project Director, Tamil Nadu Road Sector Project, Adyar, Chennai-20 The Director of Rural Development, Kuralagam, Chennai-104 The Pay and Account Officer (South), Chennai-35 The Account General, Chennai-18/35
Copy to:- SF/SC /FORWARDED BY ORDER/ SECTION OFFICER. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Annexure – 6 IMPLEMENTATION ARRANGEMENTS· The PIU is responsible for implementing the RAP in accordance with the provision of the R&R policy. The PIU has built in certain organizational and institutional capacity, by the creation of a Social Development Unit (SDU) to ensure effective implementation of RAP in a timely and appropriate manner.· | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||